This paper investigates two different semi on-line scheduling problems on a two-machine system. In the first case, we assume that all jobs have their processing times in between p and rp \((p>0, r\geq1)\). In the second case, we assume that the largest processing time is known in advance. We show that one has a best possible algorithm with worst case ratio 4/3 while LS is still the best possible for the other problem with ratio \((r+1)/2\) which is still \(3/2\) in the worst case \(r=2\).
Similar content being viewed by others
Author information
Authors and Affiliations
Additional information
Received: February 23, 1998; revised August 5, 1998
Rights and permissions
About this article
Cite this article
He, Y., Zhang, G. Semi On-Line Scheduling on Two Identical Machines. Computing 62, 179–187 (1999). https://doi.org/10.1007/s006070050020