Abstract
Delay and cost overrun are common phenomena in projects worldwide. However, these are especially severe in developing countries. In India as per MOSPI report, 235 projects out of 410 were severely affected cost overrun due to certain factors. A short questionnaire was conducted with 15 prominent factors responsible for cost overrun and forwarded to 190 constructional professionals across India. Total 85 responses were received and it was analyzed using various statistical tools such as analysis of variance (ANOVA) and factor analysis tool using SPSS. In this study, top three factors affecting cost overruns were identified such as price escalation of raw material, delay in planned activity and lack of co-ordination between construction parties which could be significantly responsible for cost overnun of construction project in India. Factor analysis method was also carried out to group the factors into three components of overall questionnaire. These components, such as client control component, project management component, and contractor control component, would be useful to the various parties involved in the construction activities. This paper also provides suggestive frameworks which have been framed after discussing with large number of construction professionals or expert.
Similar content being viewed by others
References
Avotos I 1983 Cost-relevance analysis for overrun control. Int. J. Project Manag. 1(3): 142–148. Available at: http://www.sciencedirect.com/science/article/pii/0263786383900182 [Accessed January 14, 2016]
MOSPI 2014 Infrastructure Statistics
Durdyev S, Ismail S and Bakar N A 2012 Factors causing cost overruns in construction of residential projects: Case study of Turkey. Int. J. Sci. Manag. 1(1): 3–12
KPMG 2013 Study on project schedule and cost overruns. PMI-KPMG
Frimpong Y, Oluwoye J and Crawford L 2003 Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study. Int. J. Project Manag. 21: 321–326
Kaliba C, Muya M and Mumba K 2009 Cost escalation and schedule delays in road construction projects in Zambia. Int. J. Project Manag. 27: 522–531
Kaming P F et al 1997 Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Constr. Manag. Econom. 15: 83–94
Moura H P, Teixeira J C and Pires B 2007 Dealing with cost and time in the Portuguese Construction Industry
Azhar N, Farooqui R U and Ahmed S M 2008 Cost overrun factors in construction industry of Pakistan. First International Conference on Construction In Developing Countries (ICCIDC–I) “Advancing and Integrating Construction Education, Research & Practice” August 4–5, 2008, Karachi, Pakistan, pp. 499–508
Azhar N, Farooqui R U and Ahmed S M 2008 Cost Overrun Factors In Construction Industry of Pakistan. Advancing and Integrating Construction Eduction Research & Practice, (1st International Conference on Construction in Developing Countries, Karachi, Pakistan).
Abdullah M R, Azis A A A and Rahman I A 2011 Potential effects on large mara construction projects due to construction delay. Int. J. Integrated Eng. (Issue on Civil and Environmental Engineering)
Harisweni 2007 The framework for minimizing construction time and cost overruns in padang and pekanbaru, Indonesia. University of Teknologi Malaysia
Dissanayaka S M and Kumaraswamy M M 1998 Comparing contributors to time and cost performance in building projects. Build. Environ. 34(1): 31–42
Aziz R F 2013 Factors causing cost variation for constructing wastewater projects in Egypt. Alexandria Eng. J. 52: 51–66
Rahman I A, Memon A H and Karim A T A 2013a Relationship between factors of construction resources affecting project cost. Modern Appl. Sci. 7(1): 67–75
Koushki P A, Al-Rashid K and Kartam N 2005 Delays and cost increases in the construction of private residential projects in Kuwait. Constr. Manag. Econom. 23: 285–294
Le-Hoai L, Lee Y D and Lee J Y 2008 Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE J. Civil Eng. 12(6): 367–377
Olawale Y A and Sun M 2010 Cost and time control of construction projects: Inhibiting factors and mitigating measures in practice. Constr. Manag. Econom. 28: 509–526
Kinnear P R and Gray C D 1994 SPSS for windows made simple-release 10. Psychology Press Limited
Norusis 1994 SPSS Advanced Statistics 6.1. Prentice Hall PTR
Kim J and Mueller C W 1978 Factor analysis statistical methods and practical issues. Eric M Usl., SAGE Publication Inc.
Rahman I A, Memon A H and Karim A T A 2013b. Significant factors causing cost overruns in large construction projects in Malaysia. J. Appl. Sci. 13(2): 286–293
Eshofonie B and Patience F 2008 Factors affecting cost of construction in Nigeria presented to the department of building university of Lagos Akoka, Lagos in partial fufilment of the requirements for the award of masters in construction management
Ameh O J, Soyingbe A A and Odusami K T 2010 Significant factors causing cost overruns in telecommunication projects in Nigeria. J. Constr. Develop. Countries 15(2): 49–67
Sharma S and Goyal P K 2014 Cost overrun factors and project cost risk assessment in construction industry—A state of the art review. Int. Acad. Sci. Eng. Technol. ISSN(P): 2
Omoregie A and Radford D Infrastructure delays and cost escalation: Causes and effects in Nigeria
Rosenfeld Y 2014 Root-cause analysis of construction-cost overruns. J. Constr. Eng. Manag. (DOI:10.1061/(ASCE)CO.1943-7862.0000789. © 2013 American Society of Civil Engineers.)
Mansfield N, Ugwu O and Doran T 1994 Causes of delay and cost overruns in Nigerian construction projects. Int. J. Project Manag. 12(4): 254–260
Doloi H 2013 Cost overruns and failure in project management: Understanding the roles of key stakeholders in construction projects. J. Constr. Eng. Manag. DOI:10.10(© 2013 American Society of Civil Engineers. CE)
Cheng Y-M 2014 An exploration into cost-influencing factors on construction projects. Int. J. Project Manag. 32: 850–860.
Shanmugapriya S and Subramanian K 2013 Investigation of significant factors influencing time and cost overruns in Indian Construction Projects. Int. J. Emerging Technol. Adv. Eng. www.ijetae.com. ISO Certified Journal, 9001(10)
Okpala D C and Aniekwu A N 1988 Causes of high costs of construction in Nigeria. J. Constr. Eng. Manag. 114: 233–244
Author information
Authors and Affiliations
Corresponding author
Rights and permissions
About this article
Cite this article
Wanjari, S.P., Dobariya, G. Identifying factors causing cost overrun of the construction projects in India. Sādhanā 41, 679–693 (2016). https://doi.org/10.1007/s12046-016-0498-3
Received:
Revised:
Accepted:
Published:
Issue Date:
DOI: https://doi.org/10.1007/s12046-016-0498-3