Paper
7 September 2010 The National Ignition Facility: alignment from construction to shot operations
S. C. Burkhart, E. Bliss, P. Di Nicola, D. Kalantar, R. Lowe-Webb, T. McCarville, D. Nelson, T. Salmon, T. Schindler, J. Villanueva, K. Wilhelmsen
Author Affiliations +
Abstract
The National Ignition Facility in Livermore, California, completed it's commissioning milestone on March 10, 2009 when it fired all 192 beams at a combined energy of 1.1 MJ at 351nm. Subsequently, a target shot series from August through December of 2009 culminated in scale ignition target design experiments up to 1.2 MJ in the National Ignition Campaign. Preparations are underway through the first half of of 2010 leading to DT ignition and gain experiments in the fall of 2010 into 2011. The top level requirement for beam pointing to target of 50μm rms is the culmination of 15 years of engineering design of a stable facility, commissioning of precision alignment, and precise shot operations controls. Key design documents which guided this project were published in the mid 1990's, driving systems designs. Precision Survey methods were used throughout construction, commissioning and operations for precision placement. Rigorous commissioning processes were used to ensure and validate placement and alignment throughout commissioning and in present day operations. Accurate and rapid system alignment during operations is accomplished by an impressive controls system to align and validate alignment readiness, assuring machine safety and productive experiments.
© (2010) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
S. C. Burkhart, E. Bliss, P. Di Nicola, D. Kalantar, R. Lowe-Webb, T. McCarville, D. Nelson, T. Salmon, T. Schindler, J. Villanueva, and K. Wilhelmsen "The National Ignition Facility: alignment from construction to shot operations", Proc. SPIE 7797, Optics and Photonics for Information Processing IV, 77970M (7 September 2010); https://doi.org/10.1117/12.861485
Lens.org Logo
CITATIONS
Cited by 1 scholarly publication.
Advertisement
Advertisement
RIGHTS & PERMISSIONS
Get copyright permission  Get copyright permission on Copyright Marketplace
KEYWORDS
National Ignition Facility

Mirrors

Spatial filters

Kinematics

Optical alignment

Image processing

Control systems

RELATED CONTENT

The National Ignition Facility: beam area increase
Proceedings of SPIE (February 20 2013)
Antares Beam Alignment System
Proceedings of SPIE (November 13 1980)
Operational Performance Of The Antares Alignment System
Proceedings of SPIE (August 13 1984)
Antares Beam Alignment System Performance
Proceedings of SPIE (November 07 1983)
Laser chain alignment with low-power local light sources
Proceedings of SPIE (December 08 1995)

Back to Top